NEC 705 and 706 for Apprentices: Connecting Solar and Batteries to a Panel, Supply-Side Taps, the 120% Rule and Disconnects

Updated About 7 min read

Short answer: Article 705 covers power sources that run in parallel with the utility, such as a solar inverter or a battery inverter tied to a home’s panel. You can connect on the supply side of the service disconnect (NEC 705.11) or on the load side, in a panel or feeder (NEC 705.12). A common load-side option is the 120% rule: 125% of the inverter output current plus the rating of the breaker protecting the busbar can be no more than 120% of the busbar rating, with the inverter breaker at the opposite end from the main. The power sources need a disconnecting means, and in some arrangements sources can share one (NEC 705.20), and the inverter must stop exporting when the utility goes down (NEC 705.40). Article 706 covers energy storage systems.

PSI lists Renewable Energy Technologies as a subject area on the Texas Journeyman exam: 2 scored NEC Knowledge questions and 1 scored Calculations question. PSI does not say how many cover interconnection or energy storage alone. The Texas Journeyman Practice Pack has 1,000 original questions and 10 timed mock exams in the real two-part format, with step-by-step solutions for every calculation. Try free practice questions without signing up. Get the full pack for US$39 with one payment.

Tsai Electro is an independent learning site. Not affiliated with TDLR, PSI or NFPA. We explain the ideas in our own words and do not reproduce NEC text. Check every rule and table value in your own 2026 NEC, follow the inverter and battery manufacturer’s instructions and the utility’s interconnection requirements, and follow your supervisor and the local inspector. A panel with an interconnected source can stay energized from more than one direction.

Where the rules live

TopicWhere to look
The PV array, its circuits and rapid shutdownArticle 690
Connecting any parallel source to the premises wiringArticle 705
Battery and other energy storage systemsArticle 706
GeneratorsArticle 445
Emergency and standby systemsArticles 700, 701 and 702

Supply side or load side

  • Supply-side connection. The source connects on the supply side of the service disconnecting means, often between the utility meter and the service disconnect (NEC 705.11). The exact point depends on the service arrangement and the utility’s requirements. It does not use the panel busbar, so the busbar limit does not apply. The conductors and the disconnect for the source have their own rules, similar to service conductors, and the connection method must be suitable, for example a listed connector or lugs provided for it.
  • Load-side connection. The source connects through a breaker in a panelboard or to a feeder (NEC 705.12). Here the busbar and feeder conductors can be fed from two directions, so the code limits how much current the sources can add.

The 120% rule for a panel busbar

For a load-side connection in a panelboard, the code gives a few options (NEC 705.12). The ones apprentices use most:

  • The 100% option. The sum of 125% of the inverter output current and the rating of the breaker protecting the busbar does not exceed the busbar rating.
  • The 120% option. The sum of 125% of the inverter output current and the rating of the breaker protecting the busbar does not exceed 120% of the busbar rating, and the inverter breaker is at the opposite end of the busbar from the main supply. The panel gets a warning label not to relocate that breaker.

Other options exist, such as a method based on the sum of the overcurrent device ratings with the exclusions the code lists, or a listed power control system that limits current (NEC 705.13). Each option has its own conditions. Check the full list in your 2026 NEC.

Worked example: how big a solar inverter fits on a 200 A panel

A house has a 200 A busbar and a 200 A main breaker. The inverter is 240 V and will be connected with a backfed breaker at the opposite end of the busbar from the main. Assuming the panel qualifies for the 120% option, what is the largest continuous inverter output current this calculation allows?

  1. 120% of the busbar. 200 A × 1.20 = 240 A.
  2. Room left after the main. 240 A − 200 A = 40 A. This is the limit for 125% of the inverter output current.
  3. Inverter output current. 40 A ÷ 1.25 = 32 A.
  4. Inverter size. 32 A × 240 V = 7,680 W, about 7.68 kW of inverter output.
  5. Breaker. 125% of 32 A is 40 A, and a 40 A breaker is a standard size.
  6. Check. 40 A + 200 A = 240 A, which equals 120% of 200 A and does not exceed it.

Main breaker derate. If the load calculation and the equipment listing allow the 200 A main to be replaced with a compatible 175 A breaker, the room becomes 240 − 175 = 65 A, so the calculation allows up to 65 ÷ 1.25 = 52 A of inverter output, about 12.5 kW at 240 V. The breaker, conductors and equipment still have to meet their own rules.

Disconnects and loss of the utility

  • Disconnecting means. The power sources need a means to disconnect them from all ungrounded conductors of the premises wiring, and the code allows some sources to share a disconnect (NEC 705.20). It must meet the accessibility and marking rules, and where the line and load terminals can both stay energized in the open position, it gets a warning marking.
  • Loss of the primary source. When the utility goes down, an interactive inverter must automatically stop sending power to the utility and must not reconnect until the utility is restored (NEC 705.40). This protects line workers. Systems that keep the house running in an outage do so through equipment that separates the house from the utility first.
  • Backfed breakers. Backfed plug-in breakers generally need an additional fastener under the panelboard rules, but Article 705 has an exception for some breakers backfed by interactive inverters. Check whether it applies before you order a hold-down kit.

Energy storage systems: Article 706

Article 706 covers energy storage systems, including home battery systems. For most installers the key points are:

  • Listing. The energy storage system is listed for its use, and it is installed per its listing and the manufacturer’s instructions.
  • Disconnecting means. The system needs a disconnect that isolates its ungrounded conductors from the wiring it connects to. It can be built into the system or installed separately, and Article 706 sets its location, accessibility and marking rules. Check them and the equipment instructions before you pick the spot.
  • Connection. When a battery inverter runs in parallel with the utility, the interconnection rules of Article 705 apply to it, including the busbar options above.

Location, working space and spacing rules for batteries also come from Article 706, the manufacturer and the fire code. Check them before you plan the wall.

Check yourself

  1. For the 120% option, where does the inverter breaker go? At the opposite end of the busbar from the main supply.
  2. A 200 A busbar has a 200 A main. What is the largest inverter output current under the 120% option? 32 A.
  3. What must an interactive inverter do when the utility goes down? Stop sending power to the utility automatically and not reconnect until the utility is restored.

Disclosure: If you buy through the Amazon link below, Tsai Electro may earn a commission at no extra cost to you. As an Amazon Associate I earn from qualifying purchases.

Find Articles 705 and 706 faster on exam day

NFPA 70, National Electrical Code, 2026 Edition (softcover). Highlight the load-side connection options in 705.12 and the disconnect rules in 705 and 706, since interconnection questions often mix a lookup and a busbar calculation. The Texas exam is open book. PSI allows a soft-bound NEC with highlighting, underlining and notes made in advance. Loose-leaf, spiral-bound and ring-bound copies are not allowed, and only permanent index tabs made or supplied by the NEC publisher are permitted; homemade and third-party tabs are not.

FAQ

What is the 120% rule for solar?

For a load-side connection in a panel, 125% of the inverter output current plus the rating of the breaker protecting the busbar can be no more than 120% of the busbar rating, with the solar breaker at the opposite end of the busbar from the main.

How big a solar system can I put on a 200 A panel?

With a 200 A busbar, a 200 A main and the 120% option, the inverter output current can be up to 32 A, about 7.68 kW at 240 V. A supply-side connection, a main breaker derate or another option can allow more.

What is a supply-side connection?

A connection on the supply side of the service disconnecting means, often between the utility meter and the service disconnect. It does not use the panel busbar, so the busbar limits do not apply, but the source conductors and disconnect have their own rules.

Is solar on the Texas Journeyman exam?

PSI lists Renewable Energy Technologies as a subject area, with 2 scored NEC Knowledge questions and 1 scored Calculations question. PSI does not say how many cover interconnection or energy storage alone.

Next step: practice renewable energy and calculation questions under timed exam conditions. The Texas Journeyman Practice Pack has 10 timed mock exams in the two-part format, 59 questions in 130 minutes and 26 in 110 minutes, with step-by-step solutions for every calculation. 1,000 questions, free questions to try first with no sign-up, US$39, one payment.

Next skill: solar and emergency systems. The array side and the standby side meet at the interconnection: NEC 690 solar and 700 emergency systems.

Sources checked October 2026